top of page

VVC's Syracuse Project Updates for 2022 and 2023

VVC had a couple of project advancements in the latter half of the year. PHC completed the installation of a 14-mile internal gas gathering system for the Syracuse Project which can support 100 wells and will connect over 30 planned wells. The system also contains a waste water disposal system to re-inject reservoir water produced from the gas wells. In 2021, PHC reworked a pre-existing well and connected it to the Tumbleweed Pipeline which transports the helium-rich gas to the Ladder Creek Helium plant.

Want to read more?

Subscribe to akapenergy.com to keep reading this exclusive post.

Recent Posts

See All
bottom of page