Blue Star Commences Drilling BBB#33 with Main Rig

  • AKAP
  • Jan 15, 2024
  • 2 min read

Blue Star Helium has re-entered and started drilling the intermediate hole section at BBB #33 at its Voyager field in Las Animas, Colorado. The drilling operations are expected to take 6 to 10 days to reach the planned total depth (TD) in the Lyons reservoir target. After reaching the TD, the well will undergo wireline logging for at least 2 days, followed by flow and pressure testing for at least 5 days. BBB #33 is an offset well to the BBB#1 discovery well (8.8% helium), located ~750ft away. The successful testing at BBB #33 is expected to lead to completion, with tie-in to production facilities anticipated during Q1'24.