Pulsar Helium resumed field operations at the Jetstream#1 appraisal well in its Topaz helium project following the end of spring road restrictions in Minnesota. The first step will involve road improvements and civil works, progressing to down-hole logging, well completion, and flow testing. The well, which reached a depth of 2,200ft and showed helium concentrations up to 13.8%, had been on hold due to seasonal traffic limitations but is now set to transition to a production well. All necessary contracts are in place, ensuring a smooth continuation of the project.